The project got off to a very slow start and is still at the planning stage.acquisitions for the majority of its components, with a ratedcommitment of 33% and a disbursement rate of 24%. THEdelays noted in the implementation of this project can bejustified by several aspects. It should also be noted, however, thatprogress has been made in the acquisition of certain gros markets such as that of the 400 drinking water supply systems.Notwithstanding the complaint being resolved, the engagement ratewould now be doubled
However, progress remains to be made at the level of the other largemarkets such as the 10 mini-networks and that of the platformPayGo. |