Project Notice
|
PNR |
70289 |
Project Name |
Defence of Canada Fighter Infrastructure Power Grid Modernization Project |
Project Detail |
The Defence of Canada Fighter Infrastructure (DCFI) Power Grid Modernization project will see a new 25 kilovolt underground High Voltage power line constructed on the base side of 4 Wing to both the tactical air command side and the airfield from Department of National Defence owned substation. The project will be completed in four phases, with phase one and two to begin first. |
Funded By |
Self-Funded |
Sector |
Energy, Power and Electrical |
Country |
Canada , Northern America |
Project Value |
CAD 101,200,000
|