Vietnam Procurement News Notice - 27303


Procurement News Notice

PNN 27303
Work Detail (TDT) - Due to the failure to arrange sufficient capital, some construction and installation packages under the Saline Control Sewerage Project in Ba Tri, Mo Cay Nam and Cho Lach Districts, Ben Tre Province are implemented more slowly than planned. approved plan. The implementation of salt control sluice gates in Ba Tri, Mo Cay Nam and Cho Lach districts, Ben Tre province depends heavily on capital allocation progress. Artwork: Le Tien The implementation of salt control sluice gates in Ba Tri, Mo Cay Nam and Cho Lach districts, Ben Tre province depends heavily on capital allocation progress. Artwork: Le Tien Results of contractor selection Package No. 12 Cong Kenh Lo, Cho Lach district has just been announced, slower than the approved plan for nearly 2 quarters. Some other construction and installation bidding packages are waiting for capital to continue deploying. The above package of Package 12 is issued by Ben Tre Project Management Board of Construction Projects for Agriculture and Rural Development (procuring entity) from November 27 to 17. / 12/2019. There are 3 contractors submitting bids (Bids), including: Tien Giang Construction and Investment Joint Stock Company; Nhat Quang Construction Company Limited; Joint venture of Hanoi Transport Infrastructure Construction Joint Stock Company - Ngoc A Chau Construction Joint Stock Company. In particular, JSC Investment and Construction Tien Giang reached 93/100 technical points, ranked No. 2; Nhat Quang Construction One Member Limited Company was not selected due to lack of capacity, experience and technical capacity of construction equipment. Joint venture of Hanoi Irrigation Transport Construction Joint Stock Company - Ngoc A Chau Construction Joint Stock Company won the bid, with the winning price of 29.09 billion dong. According to the contractor selection plan, the project has a total investment of VND 149,998 billion, including 4 main construction and installation packages: Package No. 109 Cong Sa Ke, Mo Cay Nam District (the bidding package price is VND 56.4 billion. ); Package 11 Cong Giong Vo, Mo Cay Nam district (the price of the package is 23.9 billion VND); Bidding package No. 12 Cong Kenh Lo, Cho Lach district (bidding package price is VND 29.3 billion; Package 13: Cong Kenh Truc (aperture B = 5m), Ba Tri district (bidding package price is VND 10.9 billion ). Out of the 4 construction and installation packages mentioned above, Package 12 and Package 13 have announced the results of contractor selection. According to the contractor selection plan, Package 12 selects contractors in the second quarter of 2019, but it is not until the end of the fourth quarter of 2019 that the bid solicitor will start announcing the bid invitation. Package 13 plans to deploy contractor selection from the first quarter of 2019. Initially, the bid solicitor started bidding notice from the end of the fourth quarter of 2018. However, the bid solicitor had to cancel the bid because the bid dossier of the contractors did not meet it. After that, it was not until the end of the first quarter of 2019 that the Package 13 started to be renewed; Until May 27, 2019 the contractor selection results of this bidding package have been announced. Package 11 plans to select contractors from the second quarter of 2019; Package 109 has a plan to organize contractor selection from the fourth quarter of 2019, but so far these two packages have not been notified by the bid solicitor to select a contractor. Talking to reporters of the Bidding Newspaper about the reason for delaying the implementation of a number of bidding packages under the Project, an official of the tenderer said that Package 12 must revise the design dossier so it is delayed to the fourth quarter. / 2019 just started organizing the contractor selection. Other construction and installation packages of the Project are also affected by the progress due to low annual capital allocated to the Project (in 2019, the project is allocated VND 15 billion), so it is impossible to implement all 4 construction packages. mounting according to the plan. It is known that in the first quarter of 2020, the tenderer will start organizing the selection of contractors for Package 11. For Package No. 109 Cong Sa Ke, due to its highest value, the implementation of this package heavily dependent on the capital allocated to the Project in 2019, the source of capital transferred to 2020, the staff of the Employer shall provide information.
Country Vietnam , South Eastern Asia
Industry Water & Sanitation
Entry Date 25 Feb 2020
Source https://baodauthau.vn/dau-thau/xay-lap-cong-kiem-soat-man-tai-ben-tre-cham-do-thieu-von-119300.html

Tell us about your Product / Services,
We will Find Tenders for you