d52032700 Bridge Maintenance Vestfold 2027-2029 . Descriptionbackground And Purpose General Bridge Maintenance In Vestfold County There Are 14 Bridges That Have Been Selected. In Special Circumstances, Bridges Can Be Deferred To Later Contracts. Contract Bridges: •07-0271 Teien: Edge Girders, Guardrail Work, Asphalt/Membrane Work, Concrete Grips. •07-0206 Revetal: Edge Girders, Guardrail Workers, Asphalt/Membrane Workers, Concrete Grabbers. •07-0208 Rimstad: Edge Girders, Railing Work, Asphalt/Membrane Work, Concrete Grabs. •07-0223 Lofstad: Edge Girders, Guardrail Work, Asphalt/Membrane Work, Concrete Grabs. •07-0515 Thrown: Edge Girders, Guardrail Workers, Asphalt/Membrane Workers, Concrete Grabs. •07-0212 Røssesund: Asphalt/Membrane Work/Concrete Grip Cover. •07-0472 Hvåra: New Steel Joints Including Concrete Grips On Back Walls/ Land Tank/Bridge Plate/Cross Beams, Drain Approx. 250M Drip Nose. •07-0009 Holmen: Reinforce Steel Beams With Steel Profiles •07-0238 Dale River: Edge Girders (Same As Before), Reuse Of E.G. Railings With Associated Railing Work, Asphalt/Membrane Work, Misc. Concrete Grip. •07-0649 Inlaget: New Guide Edges, Bridge Guardrails/Road Guardrails •07-0391 Hallenstvedt: New Guide Edges, Bridge Guardrails/Road Guardrails •07-0556 Ringveien Transition Bridge: Repair On Edge Beams, Repair Railing Posts, Wickerwork Fence, Closed Brace Holes •07-0469 Fredenshavn: Edge Girders, Railing Work, Asphalt/Membrane Work, Concrete Grip. •07-0556 Kleiva: New Leading Edges, Bridge Guardrails/Road Guardrails Other Works: Bru 50 Process-Based Applies To Additional Work On Contract Bridges, As Well As Accrued Work, Damage Cases Etc., Plus What Must Be Done Continuously And To Order From The Client On Contract Bridges And Other Bridges In The Contract Area. Quantities That Form The Basis For Bru 50 Process-Based Are Estimates And Are Highly Uncertain. The Supplier Must Also Anticipate Having To Carry Out Work Of A More Urgent Nature, E.G. Due To Flooding Or Collision. Work With Asphalt/Membrane And Surface Treatment Of Steel Must Be Carried Out Between 1 May And 1 October. Beyond This, By Special Agreement With Byggherre.Nn To Be Written.
|