Task No. 1 The Subject Of The Order Is Reconstruction Of The Municipal Road Dworcowa In Kożuchów With A Total Length Of 261.21 M. The Investment Includes The Construction Of The Surface Of The Public Road Ul. Dworcowa With A Traffic Lane Width Of 3.5 M, Made Of Starobruk Stones With A Traffic-Free Surface Between The Lanes, Approximately 1.3 M Wide. Parameters Of The Designed Road: Public Dworcowa Street At Km: 0+000.00 - 0+261.211. Road Category: Public Road2. Technical Standards Of The Road: Class L3. Design Speed: 30 Km/H4. Road Cross-Section: 1 Road With Two Lanes In Opposite Directions, With An Area Excluded From Traffic With A Width Of Approx. 1.3 M Between The Lanes5. Lane Width: 3.5M6. Assumed Traffic Load Category: Kr3. The Investment Will Include The Construction Of A Road, Roadsides, Exits, Tree Felling, Storm Water Drainage. The Reconstruction Will Include The Construction Of A Public Road At Ul. Dworcowa, 261.21 M Long, With A Traffic Lane Width Of 3.5 M, Made Of Starobruk-Type Concrete Cubes, With A Traffic-Free Surface Between The Lanes, Approximately 1.3 M Wide. The Investment Will Include Individual Exits From The Concrete Cubes To The Property And An Individual Exit From The Mma In Ul. Spółdzielcza, As Well As An Individual Exit Made Of Starobruk Concrete Cubes In Os. Kolejowe. Dworcowa Street Will Be Drained Through A Designed Storm Sewage System With 1.0 M Concrete Wells And Street Inlets. As Part Of The Investment, It Is Planned To Replace The Curbs Adjacent To The Road In Accordance With The Pzt. Task No. 2 The Subject Of The Order Is Reconstruction Of The Internal Road Of Ul. Dworcowa In Kożuchów With A Length Of Approx. 231.0 M. Parameters Of The Designed Road: 1. Road Category: Internal Road3. Design Speed: 30 Km/H4. Width Of The Traffic Lane: Approx. 3.5 M 5. Assumed Traffic Load Category: Kr3. As Part Of The Reconstruction, It Is Planned To Construct An Internal Road At Ul. Dworcowa, 231.30 M Long, With A Traffic Lane Width Of 3.5 M, Made Of Starobruk Type Paving Stones. The Investment Will Include The Following: Road, Sidewalks, Exits, Parking Spaces, Tree Cutting, Greenery, Retaining Wall, Slope Reinforcement, Storm Sewage System. Note! The Paving Stones Obtained During Dismantling Are The Property Of The Ordering Party. The Contractor Is Obliged To Transport It To The Place Indicated By The Ordering Party, Up To 5 Km From The Investment Site. The Contractor Is Obliged To Obtain, Acting Under The Authorization And On Behalf Of The Ordering Party, As Part Of This Order, A Certificate Of Acceptance Of The Notice Of Completion Of Construction For Both Tasks. The Ordering Party Has The Final Decision On The Construction Permit - Decision No. 248/2024 Of June 25, 2024 And Decision No. 300/2024 Of July 24, 2024. A Detailed Description And Scope Of Execution Of The Subject Of The Order (Both Tasks) Are Included In The Design Documentation, Which Includes Construction And Executive Designs, Technical Specifications For The Ex
|