Contract Award Notice |
|
TRR | 18301542 |
Organization | Минское Республиканское Унитарное Предприятие Электроэнергетики Минскэнерго |
Tender No | 100071593-2024-00017 |
Funded By | Self-Funded |
Country | Belarus , Eastern Europe |
Contract Value | 40,334 |
Work Detail |
Contract Award For Dc Switchboard Of Three Cabinets, Complete With Two Switchboards Consisting Of: Dc Power Supply. Distribution 1S Ab-1 With Zpu-1. Dc Power Supply. Input Ab-1 For 1 Sec. Dc Power Supply. Backup Dc And Rbr. Dc Power Supply. Input Ab-2 At 2S. Shcpt. Distribution 2S Ab-2 With Zpu-2 For The Construction Project Reconstruction Of The 110/35/10 Kv Substation Nesvizh, Construction Of A 110 Kv Overhead Line To The Nesvizh Substation From The 110 Kv Overhead Line Gorodeya Traction-Vishnevets |
Key Dates |
|
Contract Date | 23 Apr 2024 |
Contact Information |
|||||||||||||||||||||||||
View Notice Now...Login with your Social Account for Instant Access to this notice
|