Project Detail |
The project development objective is to improve the coverage of urban cadaster services in selected municipalities
to enhance local government capacities for revenue generation and urban management.
Component 1: Strengthening Municipal Systems, Services and Capacities to Generate
and Maintain Urban Cadasters in Project Municipalities 69.10
Component 2: Strengthening of the Institutional Framework 6.30
Component 3: Project Management 5.50
Project Development Objective
PDO Statement
The Project development objective is to improve the coverage of urban cadaster services in selected
municipalities to enhance local government capacities for revenue generation and urban management.
PDO Level Indicators
The PDO-level indicators to measure achievement of the PDO are as follows:
(i) 60 percent increase in the property tax base of Project municipalities (Percentage)
(ii) Number of people living in Project municipalities with access to improved hazard exposure data (4.7
million)
(iii) 75 percent of plots registered by the Project are linked to land use and zoning data (Percentage)
Section VI contains the Results Framework, including PDO-level indicators and intermediate results indicators by
component, along with corresponding baselines, intermediate, and end-of-project targets.
B. Project Components
20. The Project will work with 22 prioritized municipalities located in 4 provinces: Lima, Chiclayo,
Lambayeque and Piura. From the total of 1,874 municipalities in Peru, 22 have been prioritized for financing under
the project based on a set of eligibility criteria that include, inter alia: (i) potential for increased property tax
collection; (ii) potential for fiscal decentralization (municipalities with inexistent or outdated cadasters, significant
potential revenue gap, within main cities); (iii) areas affected by the 2017 flooding where reconstruction efforts
are taking place; (iv) rapid urban development and/or expansion; and (v) municipalities where the MVCS is
supporting the development or updating of urban plans. Interinstitutional agreements were signed between the
MVCS and the target municipalities prior to appraisal. The Project focuses only on urban areas and does not
include peri-urban or rural areas of the municipalities. Detailed Coordination Agreements will be signed by the
MVCS, COFOPRI with each municipality during the implementation stage |