The PDO is to (i) decommission the Komati coal-fired power plant, (ii) repurpose the project area with renewables, and (iii) create opportunities for workers and communities during the transition process.
Key Details
Project Details
Project ID
P177398
Status
Active
Team Leader
Franz Gerner,Frederic Verdol
Borrower 2
Eskom Holdings Soc Ltd
Country
South Africa
Approval Date
(as of board presentation)
November 3, 2022
Total Project Cost 1
US$ 497.00 million
Implementing Agency
Eskom Holdings Soc Ltd
Region
Eastern and Southern Africa
Fiscal Year 3
2023
Commitment Amount
US$ 497.00 million
Environmental and Social Risk
High
Last Update Date
October 13, 2022
Closing Date
N/A
Consultant Services required
Yes
Last Stage Reached
Bank Approved |